OUR PROJECTS
Current & Recently Completed Projects
Recently Awarded Projects:
Lincoln Business Park – Bellingham, MA – Site prep, mass grading, and rock crushing for a 345,000 SF new warehouse. Work includes erosion control, clearing, grubbing, 300,000 CY of rock cuts and fills, 130,000 CY of crushing, foundation excavation, and gravel placement.
Orange 1&2 Solar – Orange, MA – 13.7 MW Solar development. Work includes clearing, grubbing, erosion control, access road construction, grading, ponds, drainage, electrical trenching, and concrete foundations.
2019 Projects:
Hillside Logistics Park Lots A&D – Northborough, MA – 600,000 SF of new warehouse space on a large 55 acre parcel. Work includes clearing and grubbing, erosion control, 750,000 CY of fast-paced earthmoving, 10,000 LF of storm drain, 7,500 LF of domestic and fire water, 3,500 LF of sanitary sewer, miles of electric, telecom & gas, foundation excavation, 55,000 CY of gravel placed, and 10,000 tons of asphalt paving. Majority of work completed in one construction season.
150 Hayes Memorial Warehouse – Marlborough, MA – 167,000 SF of new warehouse space on a 20 acre parcel. Work includes clearing and grubbing, erosion control, 150,000 CY of fast-paced earthmoving, storm drain, domestic and fire water, sanitary sewer with pump station, electric, telecom & gas, foundation excavation, gravel and asphalt paving. All work completed in one construction season.
Hubbardston Solar – 7.5 MW Solar development on a 35 acre site. Work includes clearing, grubbing, erosion control, access road construction, mass grading, ponds, drainage, electrical trenching, and concrete foundations.
Gardner Solar – 3.2 MW Solar development. Work includes reclaiming and mass grading of a 30 acre sand and gravel pit, access road construction, ponds electrical trenching, and concrete foundations.
Wales Solar – 3 MW Solar development. Work includes clearing, grubbing, erosion control, access road construction, grading, ponds, drainage, electrical trenching, and concrete foundations.
UMass Amherst Energy Storage – 1.3 MW Energy Storage compound. Work includes site prep, excavation, road trenching, concrete foundations, backfill, and stone compound pad.
Milford Roadway Extension – Extending Deer Street. Work includes clearing, grubbing, grading, installation of a box culvert with wingwalls, sewer, water, drain, gas, electric, paving, curbing, and sidewalks.
Winchendon Solar – 2.6 MW Solar development. Work includes clearing, grubbing, erosion control, access road construction, grading, ponds, drainage, electrical trenching, and concrete foundations.
2018 Projects:
Ledgeview Way Wrentham – Mixed Use Development; Wrentham, MA – Owner – RA Ventures
Constructed a main access road and developed 5 Lots complete with blasting/processing of ledge, all utilities, paving, curbing, etc. Contract Value – $18,920,000.00.
Solar Farms – Exeter & North Smithfield RI; Palmer Ma; Athol Ma – S&C Electric; Borrego Solar
Site Preparation, grading, erosion control, drainage, ledge, gravel roads, E & B for electric, and F & I detention ponds & equipment pads. Contract Values – $807,000.00 to $1,050,000.00.
Cape Cod Aggregate – Freetown, MA – Owner – Cape Cod Aggregates
Excavate/Remove soil (overburden) above ledge and construct a new access ramp into the quarry – 100K CY Contract Value – $416,000.00.
220K SF Warehouse – Building Site Development; Northborough, MA – Owner – Gutierrez Const. Co.
Grade site with onsite moisture sensitive soils, install all site utilities and provide finishes (paving, curbing, loam/seeding, etc.) for a complete site package. Contract Value – $3,660,000.00.
TJX Companies Parking Lot Expansion – Worcester, MA – Owner – TJX Companies
Grade, drill/blast/process ledge, install drainage with pond, modify site lighting system, pavement with select gravels, finishes to include berm, markings, & signs. Contract Value – $1,800,000.00.
2017 Projects:
FedEx Distribution Facility – Middletown; CT – Contractor – Manafort Brothers
Excavate/Grade parcel to proposed subgrade elevations (2M CY) including rock. Contract Value – $8,965,000.00.
Keating Pit – Lunenburg, MA – Owner – PJ Keating
Dredge existing sediment ponds and dispose of material onsite, construct rock access “fingers” for future maintenance. Contract Value – $600,000.00.
Solar Farms – Westminster & Fitchburg, MA – Owner/Contractor – Nexamp
Site Prep, grading, erosion control, ponds, drainage, ledge, gravel roads, E&B for electric, equipment pads. Contract Value – $2,250,000.00.
2016 Projects:
Putnam Landfill – Putnam, CT – Owner – Wheelabrator Technologies
Cell Expansion/ Excavation – 500K CY; Leachate Piping, Liner, Select Layers; Process onsite materials to make select layers/materials – 60K CY. Contract Value – $3,748,000.00.
Oxford Power Plant – Earthwork/Grading; Oxford, CT – Owner – Gemma Corp.
Cut/Fill & Grade 300,000 CY Onsite. Contract Value – $1,500,000.00.
Keating Pit – Remove Overburden; Lunenburg, MA – Owner – PJ Keating
Excavate/Remove soil (overburden) above ledge and stockpile onsite – 400k CY, including erosion control Contract Value – $1,000,000.00.
Tri-State Truck Center – Shrewsbury, MA – Owner – Tri-State Truck Center
Excavate/Grade 125k CY of ledge to create building pad inclusive of drainage, detention pond expansion, and processing onsite material for gravel. Contract Value – $1,150,000.00.
Danforth Green – Housing Development; Framingham, MA – Owner – Brendon Homes
Grading & processing of onsite unsuitable materials, F&I water, sewer, & drain within the right-of-way, prepare the roadway for pavement. Contract Value – $4,121,000.00.
Various Solar Farm Projects Totaling 30Mw of Power – Owner/Contractor – Nexamp
Site prep, grading, erosion control, drainage, ledge/boulders, gravel roads, ponds, equipment pads, and E&B for electrical conduit. Contract Value – $7,850,000.00.
2015 Projects:
Shrewsbury Landfill – Cell Expansion; Shrewsbury, MA – Owner – Wheelabrator Technologies
Cell Expansion to include grading/shaping, F & I all select materials and liner, leachate piping, drainage, construction of a large segmental block retaining wall. Contract Value – $3,183,000.00.
Solar Farms – Charlton & Rutland, MA – Owner/Contractor – Nexamp
Site prep, grading, erosion control, drainage, ledge/boulders, gravel roads, construct detention ponds, F & I equipment pads, and E & B for electrical conduit. Contract Value – $1,223,000.00.
Altec – Industrial Building Site; Shrewsbury, MA – Contractor – The Stewart Perry Company
Site preparation; erosion control; cut/fills/grading (300k CY); water, sewer, & drainage systems; E&B electrical; E&B building foundation & below slab utilities. Contract Value – $4,195,000.00.
Middleboro Landfill – Cell Expansion; Middleboro, MA – Owner – Waste Management
Excavate/shape for cell expansion, install all selects including clay liner and associated leachate and drainage piping. Contract Value – $1,527,000.00.
Cranberry Crescent – Commercial Complex; Plymouth, MA – Contractor – Lawrence Lynch Corp.
Perform Cuts/Fills rough grading of site, 117k CY. Contract Value – $468,000.00.
2014 Projects:
Pleasant Valley Crossing – Retail Complex; Sutton, MA – Contractor – CJP Construction Inc.
Perform grading, site preparation, retaining walls. Contract Value – $354,000.00.
Eagle Hill School – Utility Work; Hardwick, MA – Owner – Eagle Hill School
Furnish and install a sewer forcemain system. Contract Value – $625,000.00.
Putnam Landfill – Stage 3 Cap; Putnam, CT – Owner – Wheelabrator Technologies
Process onsite material for select products required for the cap; F&I the liner system, piping, and drainage; E&B for metals recovery processing facility including below slab piping. Contract Value – $977,000.00.
Solar Farms – Winchendon & Berlin, MA – Owner/Contractor – Nexamp
Site preparation, grading, erosion control, drainage, ledge/boulders, gravel roads, construct detention ponds, F & I equipment pads, and E & B for electrical conduit. Contract Value – $1,177,000.00.
CSX Auto Distribution Facility – Spencer, MA – Contractor – Transdevelopment Group
Perform grading, cuts/fills including ledge; F&I drainage system with retention ponds; E&B for site lighting Contract Value – $6,087,000.00.
2013 Projects:
Goddard St. Parking Lot – Worcester, MA – Contractor – O’Hara Buthray Associates
Grading, retaining walls, utilities, gravels, and paving. Contract Value – $2,045,000.00.
Nexamp Solar Farms – Hubbardston & Rutland, MA – Owner/Contractor – Nexamp
Site preparation, grading, erosion control, drainage, ledge/boulders, gravel roads, construct detention ponds, F & I equipment pads, and E & B for electrical conduit. Contract Value – $2,744,000.00.
CSX Rail Siding – Westboro, MA – Contractor – Transdevelopment Group
Perform grading, cuts/fills; drainage system; E&B for site lighting; Paving. Contract Value – $833,000.00.
Scale House & Truck Wash Facilities – Shrewsbury, MA – Owner – Wheelabrator Technologies
Excavate/Backfill for buildings and truck scale structure with below slab piping, site drainage, electric, sewer/processed water; and paving with gravels. Contract Value – $1,582,000.00.
Reserve on Salisbury – Apartment Complex; Holden, MA – Owner – Reserve on Salisbury, LLC
Site preparation; grading; cuts/fills; F&I water, sewer, and drainage systems; E&B electrical & buildings including below slab piping; F&I paving, curbing, signage, etc. Contract Value – $4,645,000.00.
Shrewsbury Landfill – Cell Expansion; Shrewsbury, MA – Owner – Wheelabrator Technologies
Cell Expansion to include excavation (2M CY), grading/shaping, F & I all select materials and liner, leachate piping, and drainage. Contract Value – $19,774,000.00.